How Long a Condo or Co-op Bathroom Remodel Takes When You Live There
The Remediation Tech remodels bathrooms in occupied condo, apartment and co-op units in Greater Northeast Philadelphia, Lower Bucks and nearby Montgomery County. Residents can usually stay put. A tiled Kerdi shower takes about 5 to 8 days depending on size, complexity and building rules or access, including the membrane cure and the flood test. Surround showers can be done more quickly. The rest of the calendar depends on your building's approval, work hours and elevator schedule. We walk the unit first.
From sign-off to finish, a typical occupied-unit bath takes about 2 to 5 weeks, depending on complexity, the building's layout and management rules.
The Remediation Tech · Licensed and insured · PA HIC PA118319 · Greater Northeast Philly · Lower Bucks · nearby Montgomery County · (267) 463-8138
This page is for owners and shareholders who will live in the unit during a bathroom remodel and for the managers and boards who coordinate it. Below are the parts of the calendar we can pin down, the parts that depend on your building and how we keep the unit livable when it's the only bath. Managers can also see how we run occupied kitchen and hall bath remodels.
The timeline has two clocks
Clock one is the building. That's board or management sign-off, work hours and how materials and debris move through the building.
Clock two is the work in the unit. Surround showers can be done quickly. A tiled Kerdi shower takes about 5 to 8 days.
Many "how long" answers only count construction days. Others quote long board waits and long build windows from other markets. We confirm the rest when we walk the unit.
Board approval can take about a week, depending on the building. The work in the unit usually takes about 2 to 5 weeks, depending on complexity, the building's layout and management rules.
Why the building's clock is often longer than the crew's
Boards and managers review the scope before demo. Some buildings let management sign off on straightforward work. Others wait for a board meeting.
Restricted weekday hours and elevator windows can also stretch the calendar, even when the room itself is small.
For the forms and approvals behind that runway, see what the building usually needs first. Managers and boards can also read what condo boards check before a bathroom gut.
Board and management approval: the runway before demo
We start demo once the building has signed off on the work. Not before.
Board approval can take about a week, depending on the building. We confirm the process when we walk the unit.
We help with the alteration agreement and the scope the building wants to see. Once management approves the work, we provide a certificate of insurance naming the association or management as the building requires. That's our paperwork.
Some jobs need a permit. When one does, the local buildings department runs on its own clock. Permit time varies by township. It's typically a few days to two weeks, depending on inspector scheduling. We'll tell you what your township or city usually requires after we walk the unit.
For alteration agreements, risers, shutoffs and permits in more detail, see our condo and co-op remodel guide.
Building work hours and the elevator schedule
Every building sets its own hours. Loud work stays inside the hours your building allows. We coordinate closely with management and work within each building's policies.
We plan deliveries and work around the building's elevator schedule. Your manager or super gives us the building's windows. We plan materials, crew and debris runs around them.
When the building requires them, we use elevator pads, hallway runners and contractor check-in.
We clean the hallway and elevator path every day. Our crew hauls the debris out of the building.
We set all of this with the desk before day one.
Living in the unit when it's the only bathroom
Most residents stay in the unit. The rest of the home stays in use while one room is under construction.
When it's the only bath, there's a working toilet at the end of each work day.
We seal the work area. We protect floors and paths. Materials are staged so they don't block exits.
We clean up the work area and the hallway every day.
You have one point of contact. You get regular progress updates by text, phone or email.
We film the job on a GoPro. When we're done, you get the timelapse footage. It shows your bathroom coming together. It's also your record of what's behind the tile.
For how we run this kind of work with managers, see occupied kitchen and hall bath remodels for property managers and boards. For a printable list of what to confirm before demo, use our property manager planning checklist.
Construction: the shower and the rest of the bath
Here's the timing we stand behind.
Surround showers can be done quickly.
A tiled shower with a Kerdi pan takes about 5 to 8 days depending on size, complexity and building rules or access. That includes the membrane cure and the flood test.
We use Schluter Kerdi only. We flood test before tile goes on. Photos of the waterproofing are available on request.
The rest of the bath follows a set order:
- Demo
- Rough-in
- Waterproofing and the flood test
- Tile
- Fixtures and finish
How long each step takes depends on the room and the building. We give you a clear schedule before work starts.
For more on the membrane and the flood test, see condo shower waterproofing before tile.
Looking for cost? See our unit packages. This page sticks to time.
How a bathroom job runs with TRT
- We walk the unit with you. Management can join when the desk wants to be there.
- You get a written scope before anyone starts.
- Building policies, work hours and the elevator schedule are confirmed before demo. Deliveries are planned around that schedule.
- Our paperwork goes to management once they approve the work.
- One crew sees the job through, with regular progress updates by text, phone or email.
- Every change gets a signed written change order.
- Daily hallway cleanup. A working toilet each night when it's the only bath. GoPro timelapse footage handed over at the end.
Where we've worked
Buildings we've worked in include Residences at Dockside (bathrooms).
Ready to plan yours? Call or text (267) 463-8138 and we'll walk the unit.
Where we work
We remodel bathrooms in occupied condo, apartment and co-op units across Greater Northeast Philadelphia, Lower Bucks and nearby Montgomery County. We also work in selected Philadelphia condo and co-op buildings.
FAQs
How long does a tiled shower take in a condo bathroom remodel?
A tiled shower with a Kerdi pan takes about 5 to 8 days depending on size, complexity and building rules or access. That includes the membrane cure and the flood test. Surround showers can be done more quickly. We walk the unit first and give you a clear schedule before work starts.
Can I stay in my unit if it's the only bathroom?
Usually, yes. Most of our condo, apartment and co-op jobs are in homes where people are still living. We seal off the work area, clean the hallway every day and leave a working toilet at the end of each work day when it's the only bathroom. You get regular progress updates by text, phone or email.
How do you handle the elevator during a condo bathroom remodel?
We plan deliveries and work around the building's elevator schedule. Your property manager or super tells us the building's windows and we plan around them. We use elevator pads when the building requires them. We leave the elevator and hallway clean after each use.
Do you flood test the shower before tile?
Yes. We use Schluter Kerdi waterproofing only and we flood test before tile goes on. Photos of the waterproofing are available on request, so you and the building can see what's behind the tile.
How will I know what's happening during the job?
You have one point of contact. You get regular progress updates by text, phone or email. We film the job on a GoPro and give you the timelapse footage when we're done. Every change gets a signed written change order.
What paperwork do you give the building?
We're licensed and insured, PA HIC PA118319. Once management approves the work, we provide a certificate of insurance naming the association or management as the building requires. That's our paperwork. For what buildings usually ask for before work starts, see our condo and co-op remodel guide.
How long does board or management approval take?
Board approval can take about a week, depending on the building. Some buildings let management sign off on straightforward scopes. Others wait for a board meeting. We confirm the process when we walk the unit. We start demo once the building has signed off.
Planning a condo or co-op bathroom remodel? Planning a condo or co-op bathroom remodel in a building where you'll be living during the work? Call or text (267) 463-8138. We'll walk the unit, confirm the building's policies and elevator schedule before demo and give you a clear schedule so you can stay put.
Download the planning checklist
Call or text (267) 463-8138 · Licensed and insured · PA HIC PA118319 · Greater Northeast Philly · Lower Bucks · nearby Montgomery County